Dismantling: second belay point and evacuation system with the ZIGZAG

Expert Techniques

The ZIGZAG is set up in double mode on a choked false crotch.

Warning

  • Carefully read the Instructions for Use referenced in this Tech Tip before reading the Tech Tip itself. You must have read and understood the Instructions for Use to understand this supplementary information.
  • Performing these techniques requires specific training. Work with a professional to confirm your ability to perform these techniques safely and independently before attempting them unsupervised.
  • We provide examples of techniques related to your activity. Other techniques not described here may also exist.



Note: in this document the name ZIGZAG means either the ZIGZAG or ZIGZAG PLUS models.

During cutting operations, the arborist must use two belay systems.

The positioning lanyard is the first system.

The ZIGZAG, installed on a choked anchor, serves as the belay system as well as the evacuation system.

Quite simple in appearance, this configuration requires the arborist to choose between two risks when positioning his ZIGZAG.

- Low ZIGZAG setup (knee level): if the positioning lanyard breaks, risk of a significant fall (impact force greater than 6 kN).

Low ZIGZAG setup.

- High ZIGZAG setup (close to the positioning lanyard): risk of simultaneously cutting the two belay systems.

High ZIGZAG setup.